2013年8月10日星期六

The Best GIAC GCPM exam practice questions and answers

IT-Tests.com's GIAC GCPM exam training material is the best training materials on the Internet. It is the leader in all training materials. It not only can help you to pass the exam , you can also improve your knowledge and skills. Help you in your career in your advantage successfully. As long as you have the GIAC GCPM certification, you will be treated equally by all countries.


GCPM exam is a GIAC certification exam and IT professionals who have passed some GIAC certification exams are popular in IT industry. So more and more people participate in GCPM certification exam, but GCPM certification exam is not very simple. If you do not have participated in a professional specialized training course, you need to spend a lot of time and effort to prepare for the exam. But now IT-Tests.com can help you save a lot of your precious time and energy.


In order to prevent your life from regret and remorse, you should seize every opportunity which can change lives passibly. Did you do it? IT-Tests.com's GIAC GCPM exam training materials can help you to achieve your success. We can help you pass the GIAC GCPM exam smoothly. In order not to let success pass you by, do it quickly.


Exam Code: GCPM

Exam Name: GIAC (GIAC Certified Project Manager Certification Practice Test)

How far the distance between words and deeds? It depends to every person. If a person is strong-willed, it is close at hand. I think you should be such a person. Since to choose to participate in the GIAC GCPM certification exam, of course, it is necessary to have to go through. This is also the performance that you are strong-willed. IT-Tests.com GIAC GCPM exam training materials is the best choice to help you pass the exam. The training materials of IT-Tests.com website have a unique good quality on the internet. If you want to pass the GIAC GCPM exam, you'd better to buy IT-Tests.com's exam training materials quickly.


As we all know, IT-Tests.com's GIAC GCPM exam training materials has very high profile, and it is also well-known in the worldwide. Why it produces such a big chain reaction? This is because IT-Tests.com's GIAC GCPM exam training materials is is really good. And it really can help us to achieve excellent results.


GIAC certification GCPM exam is one of the many IT employees' most wanting to participate in the certification exams. Passing the exam needs rich knowledge and experience. While accumulating these abundant knowledge and experience needs a lot of time. Maybe you can choose some training courses or training tool and spending a certain amount of money to select a high quality training institution's training program is worthful. IT-Tests.com is a website which can meet the needs of many IT employees who participate in GIAC certification GCPM exam. IT-Tests's product is a targeted training program providing for GIAC certification GCPM exams, which can make you master a lot of IT professional knowledge in a short time and then let you have a good preparation for GIAC certification GCPM exam.


Through the GIAC certification GCPM exam method has a lot of kinds, spend a lot of time and energy to review the GIAC certification GCPM exam related professional knowledge is a kind of method, through a small amount of time and money IT-Tests.com choose to use the pertinence training and exercises is also a kind of method.


GCPM (GIAC Certified Project Manager Certification Practice Test) Free Demo Download: http://www.it-tests.com/GCPM.html


NO.1 You work as a project manager for Xxxx Inc. You are performing steps to carry out and finish the
project according to the measures drawn through the planning stage. Which of the following stages of the
project are you working on?
A. Monitoring and controlling
B. Closing
C. Initiation
D. Execution
Answer: D

GIAC test answers   GCPM pdf   GCPM questions

NO.2 Which of the following is described in the statement below.?
"It is a group of sequential and related project phases that are defined by the organization and control
needs of the management or organizations concerned with the project, the nature of the project itself, and
the application area."
A. Verify scope
B. Project charter
C. Activity list
D. Project life cycle
Answer: D

GIAC study guide   GCPM certification   GCPM   GCPM   GCPM exam

NO.3 Charlie has just completed the project according to the terms of the contract. She and the customer
are completing a walk through of the project deliverables, and the customer is asking for changes to the
deliverables before she'll accept the product. What project management process should manage the
documented change request that may come from scope verification?
A. Scope management
B. Perform integrated change control
C. Control Scope
D. Control change control
Answer: B

GIAC   GCPM braindump   GCPM braindump   GCPM braindump

NO.4 You work as a project manager for Xxxx Inc. You are performing a task to generate a hierarchical list of
resources related by function and resource type that is used to facilitate planning and controlling of project
work. Which of the following components of project management will you use to accomplish the above
task?
A. PERT chart
B. RBS
C. Gantt chart
D. WBS
Answer: B

GIAC   GCPM exam   GCPM test questions

NO.5 James works as the project manager for a software project. He and his team are on the Direct and
Manage Project Execution process. All of the following are inputs of this process except for which one?
A. Project charter
B. Organizational process assets
C. Enterprise environmental factors
D. Approved environmental requests
E. Project management plan
Answer: A

GIAC   GCPM   GCPM   GCPM questions   GCPM certification training   GCPM test

NO.6 You work as a project manager for Xxxx Inc. You are working on several projects. Your projects vary in
size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can
compare relative schedule and cost performance of each project. Which of the following components of
EVM provide measures of schedule and cost performance that are not affected by the size of the project?
A. BAC and EAC
B. CPI and SPI
C. CV and SV
D. PV and EV
Answer: B

GIAC   GCPM dumps   GCPM test answers

NO.7 Which of the following techniques is described in the statement below?
"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid
of any resource limitations by performing a forward and backward pass analysis through the schedule
network."
A. Resource utilization
B. Critical path method
C. Critical Chain method
D. Resource leveling heuristic
Answer: B

GIAC   GCPM certification   GCPM   GCPM answers real questions   GCPM

NO.8 You work as a project manager for BlueWell Inc. Which of the following techniques will you use to
determine whether particular work can best be accomplished by the project team or must be purchased
from the outside sources?
A. Expert Judgment
B. Make-or-Buy Analysis
C. Contract Types
D. Procurement Negotiations
Answer: B

GIAC   GCPM   GCPM answers real questions

NO.9 You are the project manager for your organization. Marcy, a project stakeholder, is demanding that you
add some deliverables to your project scope for free. You explain to Marcy that it's too late in the project
execution to consider adding these deliverables, as most of the software your project team is creating is
nearly done. Marcy and you escalate the issue to management.
Management decides that you will add the deliverables to the project scope if Marcy pays a significant fee
and allows you additional time to complete the project. What conflict resolution method has management
offered?
A. Issue management
B. Compromising
C. Forcing
D. Confronting
Answer: B

GIAC test   GCPM certification   GCPM

NO.10 You are a new Project Manager that has been entrusted with a software development project that is in
progress. A sub-contracting company has been awarded a cost reimbursable contract to do the
development work on this project, and the project has been completed. While trying to close this
procurement, you discover that still there are some unresolved claims. However, the sub contract
company does not accept that these claims are unresolved. Which of the following is the best method for
reaching the final equitable settlement?
A. Litigation
B. Mediation
C. Direct negotiation
D. Alternative dispute resolution
Answer: C

GIAC   GCPM original questions   GCPM   GCPM   GCPM exam   GCPM

NO.11 You are a Project Manager in your organization who is managing a considerably huge budget project
to develop new software. Considering the varied nature of your stakeholder group, you would like to put
together a plan as to what information the stakeholders need, and how to provide that information. What
is the document that you would need, and as part of which process group would you achieve this?
A. Communications Management Plan, Execution Process group
B. Project Management Plan, Planning Process Group
C. Communications Management Plan, Planning Process Group
D. Project Management Plan, Initiating Process Group
Answer: C

GIAC   GCPM dumps   GCPM test   GCPM   GCPM braindump

NO.12 Which of the following processes describes the statement below?
"It consists of the processes required to ensure that the project contains all the work required to complete
the project effectively."
A. Project communications management
B. Project scope management
C. Risk management
D. Project human resource management
Answer: B

GIAC certification training   GCPM   GCPM   GCPM   GCPM exam

NO.13 You work as a project manager for Xxxx Inc. Which of the following stages of the process group, if not
performed well by you, is unlikely that the project will be successful in meeting the business needs?
A. Monitoring and controlling
B. Initiation
C. Executing
D. Planning and design
Answer: B

GIAC   GCPM exam   GCPM   GCPM

NO.14 Which of the following is described in the statement below?
"It is a tool that defines a project and groups the project's discrete work elements in a way that helps
organize and define the total work scope of the project."
A. WBS
B. RBS
C. Gantt chart
D. Critical path
Answer: A

GIAC   GCPM   GCPM

NO.15 Which of the following processes formally permits the initiation of a project and marks the kickoff for all
consequent development activities to begin?
A. Develop project scope statement
B. Develop project management plan
C. Develop project charter
D. Develop project team
Answer: C

GIAC test   GCPM   GCPM exam   GCPM

NO.16 You work as a project manager for Xxxx Inc. A new project has been proposed to change all keyboards
of every computer in your organization. There are 1,600 keyboards that will need to be removed and
replaced with wireless keyboards. What document will you first need to start this project?
A. Project risk statement
B. Risk register
C. Project charter
D. Contract for new keyboards
Answer: C

GIAC   GCPM test questions   GCPM test

NO.17 You work as a project manager for Xxxx Inc. You report the project details directly to the vice president
and the administrator of your organization. In which of the following types of organization structures are
you working?
A. Functional
B. Matrix
C. Jury
D. Projectized
Answer: B

GIAC   GCPM test   GCPM certification   GCPM questions   GCPM

NO.18 You are the program manager for your project. You are working with the project managers regarding
the procurement processes for their projects. You have ruled out one particular contract type because it is
considered too risky for the program. Which one of the following contract types is usually considered to be
the most dangerous for the buyer?
A. Cost plus incentive fee
B. Time and materials
C. Cost plus percentage of costs
D. Fixed fee
Answer: C

GIAC study guide   GCPM   GCPM questions   GCPM

NO.19 You work as a project manager for Xxxx Inc. You are in the project kickoff meeting. Which of the
following documents are reviewed during the project kickoff meeting?
Each correct answer represents a complete solution. Choose all that apply.
A. Project budget
B. Project WBS
C. Project charter
D. Project scope
Answer: A,C,D

GIAC test answers   GCPM   GCPM

NO.20 Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the
project planning processes is now coming into fruition. What individual should respond to the risk with the
preplanned risk response?
A. Diane
B. Risk owner
C. Subject matter expert
D. Project sponsor
Answer: B

GIAC   GCPM test questions   GCPM exam dumps

NO.21 Which of the following are the characteristics of the project life cycle?
Each correct answer represents a complete solution. Choose all that apply.
A. Cost and staffing are low at the start, are high as the work is carried out, and decrease as the project
comes towards the end.
B. Stakeholders influences, risk, and uncertainty are at peak in the beginning of the project.
C. Skills to influence the final characteristics of the project's product, without much impact on cost, is at
peak in the beginning of the project and reduces as the project progresses towards completion.
D. It is limited by constraints, including resource constraints.
Answer: A,B,C

GIAC demo   GCPM   GCPM exam prep   GCPM   GCPM original questions   GCPM

NO.22 Which of the following processes formally permits the initiation of a project and marks the kickoff for all
consequent development activities to begin?
A. Develop project charter
B. Develop project management plan
C. Develop project scope statement
D. Develop project team
Answer: A

GIAC practice test   GCPM   GCPM   GCPM

NO.23 You are using the PDCA model to determine, implement, monitor, control, and maintain Information
Security Management System or ISMS. You have to evaluate the new processes and match up to the
results against the probable results to determine the differences. In which of the following phases of the
PDCA are you working?
A. Do
B. Act
C. Plan
D. Check
Answer: D

GIAC test questions   GCPM original questions   GCPM dumps   GCPM test questions   GCPM

NO.24 You work as a project manager for Xxxx Inc. You are working on a project that has a budget of
$805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have
actually spent $430,000 of the budget. Management wants to know the project's cost performance index.
Which of the following values will you report?
A. 0.87
B. 0.80
C. 0.84
D. 0.86
Answer: C

GIAC   GCPM study guide   GCPM   GCPM

NO.25 You work as a project manager for Xxxx Inc. Which of the following processes will you use to formalize
the acceptance of the completed project deliverables?
A. Verify scope
B. Report performance
C. Expert judgment
D. Perform quality control
Answer: A

GIAC questions   GCPM test answers   GCPM practice test   GCPM   GCPM demo

NO.26 You are in a project to create a Website. Your project team has met a few times and you're working
with them to develop the project's WBS. Jan, a marketing expert, is in disagreement with Larry over how
the Website should function. Gary and Gina are in disagreement over who'll take the lead on the design of
the software for the Website. Mark, Mary, and Martha are all bickering about the photo management
approach for the Website's pictures. What stage of team development is your project team currently in?
A. Forming
B. Storming
C. Performing
D. Norming
Answer: B

GIAC exam simulations   GCPM   GCPM practice test   GCPM

NO.27 Which of the following components of EVA is described in the statement below?
"It is a measure of how much of the project value has been earned so far through completed work, that is,
the budgeted cost of the work that has been performed through the project status date."
A. PV
B. AC
C. SV
D. EV
Answer: D

GIAC   GCPM   GCPM answers real questions   GCPM original questions   GCPM

NO.28 Which of the following are the characteristics of a project?
Each correct answer represents a complete solution. Choose all that apply.
A. Its success is measured by evaluating whether it meets or exceeds expectations of the stakeholders.
B. It is temporary in nature and has a definite beginning and ending date.
C. It is completed when the project goals are achieved.
D. It is common in nature.
Answer: A,B,C

GIAC   GCPM   GCPM braindump

NO.29 You work as a project manager for Xxxx Inc. You have to subdivide project
deliverables and project work into smaller, more manageable components. Which of the following
processes will you use to perform the above task?
A. Create WBS
B. Verify scope
C. Control scope
D. Define activities
Answer: A

GIAC exam   GCPM   GCPM   GCPM pdf

NO.30 You are the project manager of the NHT Project. This project has 12,345 office doors to install
throughout a campus. Each of the doors costs the project $456 and requires special hardware to
electronically lock and open the doors. You've gathered the project team before they begin the installation
for a hands-on training. As a group you and the project team install 50 doors following a checklist of
instructions so that every door will be installed exactly the same throughout the campus and with minimal
waste. This is an example of what project execution technique?
A. Preventive action
B. Implemented corrective action
C. Quality control
D. Defect repair validation
Answer: A